Home

  With Policy Support NTPC can Turn Darkness to Light
 
The DayAfter
Think Tank Face-to-Face with C. P. Jain
 
 

This time, the face-to-face was with C. P. Jain, Chairman and Chief Executive Officer of the major player in the power sector, the National Thermal Power Corporation. The DayAfter Editor-in- Chief Sunil Dang and the Think Tank Director, Yogendra Bali, asked sharp questions about the power problems in the country. Jain answered the questions with calm and composed confidence, a competent professional, and said that with adequate policy support he was hopeful that NTPC could play its part in leading India from darkness to light.

In this face-to-face, the Think Tank posed the question which the whole country was asking: When would the era of power shutdowns and cutdowns end and what were the hopes of seeing an end to the continuing power crisis in the country?

He said, at present, the NTPC was providing about 20 per cent of the country’s power needs. In the 10th and the 11th Five-Year plans, it proposed to add at least another 20,000 megawatts. This was part of the overall power plan of the Government. He said the NTPC’s present generation capacity was 20,000 megawatts and in another 10 years it was sought to be doubled.

The NTPC Chairman said with confidence: "We will play our role in the overall plan of the Government." What was the source of his confidence? His accurate assessment of the problems of the power sector and his hard-boiled professional approach to tackling them.

Talking about the ‘NTPC Success’, he said: "We are well-placed so far as the physical side of the plan is concerned". The NTPC had almost 4,800 MW under construction. There was technological capability available for creating plans for another 11,800 MW. They had submitted projects totalling 4,000 MW for approval. Thus, the Corporation was gearing itself to create another 20,000 MW in addition to its present capacity in the next 10 years.

The NTPC Chief agreed that the Corporation faced two critical issues. One was that of collection of revenue. The success in revenue collection was sought to be achieved through a novel "Time-Sharing Project" in which the most important element was "One-Time Settlement".

When it was pointed out that there were States and State Electricity Boards like those in Uttar Pradesh, Bihar and elsewhere which were perpetual defaulters and was he really confident that he would manage to collect dues from them, he expressed the hope that the One-time Settlement Project and the bonds would yield results from there also. He said he was conscious that they did not have the money today to pay their dues in cash. But they could pay through these bonds, which would be encashable when they had the money in due course. The bonds were expected to mature between the sixth and the 15th year, which was a sufficiently long period to enable them to pay their dues. It was like getting a post-dated cheque form the defaulter customers.

Jain’s view was that if there was a problem, a solution had to be found for it and in that, "we have to make some sacrifice, like waiving off 60 per cent surcharge and giving a further 21 per cent discount in surcharge on payment. There is substantial sacrifice in this but the thing is that the payment will come from the 6th to the 15th year. He called it ultimately a "Win-Win Situation" for the NTPC.

He agreed that the 10-year perspective plan of the NTPC required about Rs. 100,000 crore for implementation. This money he expected to raise partly from the NTPC’s own resources and partly from loans. The second critical issue was linked with this question of resource generation. Resources would be bolstered by the Corporate Tariff Plan of NTPC which was prepared as far back as 1998..

The second issue would be solved by a Tariff Formula which would take care of the cash flow to the company. This formula was applicable to all at par earlier. Every generator was guided by that formula; now the CRC has come up with separate norms for Central Public Sector undertakings like the NTPC. "That will take care of some of our cash flow. On these two assumptions, the NTPC based its 40,000 MW capacity plan. It was a resources-based plan," said Jain.

The Regulatory Commission, however had created new headaches for NTPC. Its guidelines had reduced the assumed cash flow to 30 per cent of what the plan had assumed. Time escalation was not the issue here. The problem was if you do not have the money, you will not start. The company will not start any project unless it was sure of its resources. With the resource generation reduced, the borrowing capacity would also be reduced, because it depended on the company’s repayment capacity and that capacity, again, depended upon how much the company could earn.

Right now, the NTPC was caught in a vicious triangle. But there were two redeeming factors. Taking advantage of the legal process, the Corporation had gone in appeal to the High Court. When the power sector was already short of funds, it would have to be helped out of the situation. It was not only NTPC, the policy would affect other investments also. Because the State would also have to generate certain resources. What was crucially needed was strong policy support.

   
 

Others Interviews

  Syed Shahnawaz Hussain

Pawan Kumar Chamling

Digvijay Singh

Sheila Dikshit

Tibetan Prime Minister-in-Exile Sandhong Rinpoche

Shatrughan Sinha

Eduardo Faleiro

Ramesh Bains

Ved Prakash Goyal

C. P. Jain

 

Former Prime Minister of India

  P. V. Narasimha Rao

I. K . Gujral

V. P. Singh

Chandra Shekhar

Deve Gowda

Top